Projects‎ > ‎

Project4 - Main Building

   
New Rilke Schule Location - Sentry Drive 

Building Update: 

The scope of this project is less than expected, so we have hired a contractor to complete the project instead of using parent volunteers.  However, there are a couple of projects inside the building that will require parent help.

The current tenants in the building are in the process of moving out.  With that said, some hallways and classrooms will be repainted and carpets are scheduled for cleaning. We have decided to replace the carpet in two classrooms on the third floor and the hallway.           

What are the Dates?

Contractor will begin work the week of June 28.  Carpet cleaning will begin for the stairs and hallways.  Replacement carpet for third floor is being sourced for immediate install.   

What is Needed?

We need volunteer help for the following projects: 
  • 6 people to remove small stage and small closet 
  • 6 people to remove two non-bearing walls 

Who do I Contact?

The Project Lead for this effort is Brett Wilbanks at 529-2993.